Construction estimating
How to Measure Cabinet and Countertop Quantities for a Kitchen Remodel Bid
By Plan to Price Estimating ·
A dishwasher opening takes 24 inches out of a cabinet run, but the counter usually continues over it. That one detail explains why a kitchen bid needs two takeoffs. Measure the cabinets in linear feet (LF) and the finished countertop in square feet (SF). Use the same dimensioned sketch for both.
How to measure kitchen cabinet linear feet
Label each wall, island and peninsula on the sketch. For each straight run, record its length in inches, deduct the openings on that run, then divide by 12. Keep separate lines for base, wall and tall cabinets. A pantry occupies its own footprint. A cabinet above a refrigerator belongs on the wall-cabinet line if the elevation shows one.
Mark the actual appliance widths from the specifications. Deduct a freestanding range and dishwasher from the base run. A drop-in cooktop can sit over a base cabinet, so check the cabinet schedule before taking a deduction. For uppers, measure the banks shown on the elevation around windows, the hood and tall units.
Assign the inside corner to one run and start the return at its edge. Record fillers, end panels, finished sides and the corner unit by item. Linear feet help compare layouts. Order cabinets by unit number, width, height, depth and door handing.
How to calculate countertop square feet for a bid
Divide the top into rectangles that meet edge to edge. For each, multiply length in inches by finished depth in inches and divide by 144. Include overhangs, especially on a seating island. Measure backsplash by length and height, and finished edges by linear feet. Mark sink and cooktop cutouts for fabrication and confirm how the shop bills them. This countertop estimating worksheet shows how to sketch an L-shaped layout.
Worked example for a small L-shaped kitchen
Both walls are measured into the inside corner. Wall A is 120 inches with a 30-inch freestanding range at the outer end. Wall B is 96 inches with a 36-inch refrigerator at its outer end. Assume 24-inch-deep bases, 25½-inch finished perimeter tops and a separate 72-by-36-inch island with a single 72-inch cabinet bank. This simplified layout has no dishwasher or tall cabinet.
| Section | Base run | Countertop rectangle |
|---|---|---|
| Wall A, including corner | (120 − 30) ÷ 12 = 7.50 LF | 90 × 25.5 ÷ 144 = 15.94 SF |
| Wall B, beyond corner | (96 − 36 − 24) ÷ 12 = 3.00 LF | (96 − 36 − 25.5) × 25.5 ÷ 144 = 6.11 SF |
| Island | 72 ÷ 12 = 6.00 LF | 72 × 36 ÷ 144 = 18.00 SF |
| Total | 16.50 LF | 40.05 SF |
The return starts 24 inches from the corner for the base footprint and 25½ inches from the corner for the top. Measure upper cabinets independently. For example, if the elevation shows two separate upper banks of 84 and 60 inches clear of openings, record 12 LF of wall cabinets.
Turn the takeoff into a purchase quantity and a proposal
Keep 40.05 SF as the measured top. If you carry 15% for preliminary planning on this example, the estimate carries about 46.05 SF using unrounded dimensions. A fabricator still needs the piece dimensions, available slab sizes, seam locations and vein direction to confirm yield. A long island can require another slab even when the total square footage appears to fit.
For an undecided finish, identify the material category, covered area, dollar allowance, whether fabrication and installation are included, and how credits or overages are calculated. In the internal estimate, keep the supplier quote, crew hours, overhead and markup. In the proposal, show the selling price and the scope the customer can verify. For example, describe the two perimeter sections and island, the assumed finished depths, the edge profile and who supplies the sink. See how to write clear inclusions and exclusions.
Before you price the kitchen
- Date the plan and reconcile it with field measurements.
- Check appliance openings, corner treatment and the cabinet schedule against the elevations.
- Confirm overhangs, finished edges, cutouts, backsplash and templating with the fabricator.
- Identify who supplies fixtures and appliances, who handles removals and connections, and which repairs or permit costs are included.
- Review the allowance and adjustment terms alongside the selling price.
Related guides cover small GC remodel scope, waste factors in quantity takeoffs and an estimate prepared from bathroom measurements.
Send your kitchen measurements, photos and scope notes for a quantity takeoff, internal estimate or separate branded proposal. Starting prices apply to small, clearly defined single-trade scopes. Every project receives a formal written quote confirming price, deliverables and timeline before work or payment begins. Request a written service quote.